Akköy II Penstock and HEPP

The Highest Head Project of Turkey (Hnet = 1220.00 m)

Location: Giresun – Gümüşhane
Purpose: Energy
Penstock Lenght: 3.958.00 m
Penstock Diameter: 2.70 m
Penstock Thickness: 12.00 mm – 150.00 m
Installed Power: 233.58 MWm / 229.68 MWe
Number of Units: 2
Turbine Type: Vertical Axis Pelton
Total Project Discharge: 21.00 m³/s
Net Head: 1220.00 m
Annual Energy Production: 900.00 GWh
Client: Kolin İnşaat